New Campbell Care Building

Under Construction

You may have noticed the green fencing on the blacktop near the Payne Avenue gate.  Construction on a new Campbell Care Building is beginning and should be finished by the end of March.  There will be some disruption during the school day, however every effort will be made to minimize this disruption.  The plan calls for installing water lines, sewer lines, and electrical and laying a foundation.  During our two week December break, 6 modular sections will be brought in that will make up the large three classroom building.  At that point, most of the work will move to inside the building with some landscaping and final touches outside.

We thank you for your patience and understanding during this construction time.